The revisions to the 1995 version of Approved Document L Conservation of Fuel and Power introduced in April 2002 have been introduced as part of the government's programme to reduce the effects of global warming by limiting greenhouse gas emissions wherever possible. In construction this means reducing fuel consumption by energy efficient design of the complete building fabric, limiting heat loss through thermal bridging in the structure and limiting air leakage through the building envelope. The details below have been set out to clarify the requirements for Part L2 ie non-domestic buildings.

Details of methods for showing compliance are available in the Approved Document itself, the MCRMA Technical Paper 14. This can normally be obtained from their website www.mcrma.co.uk

Two factors requiring consideration in order to establish compliance with Approved Document (AD) L2 are the U-value requirements of . 25 W/m²_k and the f-factor required to prevent condensation risk on the internal surfaces of the building.

You are required to consider the two elements of the building envelope: plane elements and linear details. Plane elements require U-value and f-factor calculations. Details require f-factor and Psi-value figures which will be dealt with seperately.

Various systems can be modelled in accordance with the Approved Document L2 using Trisco, a three-dimensional sofware package which is fully compatible with BN EN ISO 10211-1/10211-2. The heat flows must be modelled in this manner for all standing seam systems which contain repeating point thermal bridges ie clips or halters in the plane element. The effect of insulation tucked under bar and bracket systems is covered in the model.

The U-value is then calculated from these results.

Humidity

The point thermal bridges caused by brackets (ie Ashgrid) or fasteners in plane elements do not lower the f-value below 0.9 which mean they would not impose a risk of internal surface condensation with Humidity Classes 1 to 5.

In the case of air conditioned buildings in which the internal humidity is controlled independently of the external environment the set values of the temperature and humidity should be used to calculate the internal moisture load.

Following research commissioned be the MCRMA, the BRE report of 2000 concluded that " metal liners provide an effective vapour control layer in twin skinned metal roofing construction. So long as the cladding is installed to a reasonable standard with a well sealed liner, it is not necessary to use a separate plastic VCL or breather membrane in most applications."

With more complex build-ups in very high temperature/humidity buildings, extra precautions are still needed in both built-up and composite systems. Constructions using structural decks usually require a separate VCL.
 

Details

The f-factors and Psi-values performances are required to limit heat loss through linear thermal bridges. This is heat loss through the thermal bridge over and above the heat loss through adjoining plane elements. The Psi-value is used to establish the heat loss through linear thermal bridges such as ridge details, valley gutters etc. The total Psi-value should not exceed 10% of that through the plane areas as specified in IP17/01.
If this figure is exceeded then it is necessary to modify individual details to reduce the loss through the bridges.

 Standard details of "robust" details are also given in MCRMA Technical Paper 14.

In order to determine the total heat loss through the Plane Area , the square meterage of each plane element is multiplied by its U-value to give the total loss (AU) and the AU values added to achieve the total.

The total of the Psi-values for the thermal bridges is then determined by multiplying the length of each bridge by its Psi-value. The figures are then added together to give the new total linear Psi-value.
 

Thermographic Surveys

It is much better to remove the need for a survey by demonstrating to a client that the cladding has been properly designed and installed than to run the risk of potential delays and contractual difficulties due to subjective interpretation and limiting factors of a practical nature. Please refer to MCRMA Technical Paper 14.

Air Permeability

It will be necessary to demonstrate compliance with a report from a "competent person" that appropriate design details and construction techniques have been used or for buildings over 1000 M² floor area, to carry out an air leakage teat. The acceptable limit is 10M²/Hour/M² at 50 pascals. This comes into force fully as of 30th September 2003.

It has been shown in tests carried out by the BRE that correctly installed built-up systems, incorporating sealed profiled metal liners, to form an effective vapour control layer in twin-skinned metal roof constructions, can be expected to achieve an air permeability well within the limit. An example calculation is given in MCRMA TP 14 giving a result as low as 0.23m³/h/m².

Project specific advice should be sought  where separate VCL's are required or if there is any doubt as to requirements. We recommend that side and end laps/joints and all perimeter joints should be effectively sealed, not only to reduce air leakage but to provide vapour control. Attention must be paid to leakage through all other associated elements within the envelope. It is also important to remember that all other parts of the building need to comply.

However well designed a system is, it will fail and require expensive retesting, possibly delaying completion of the contract by many weeks, if it has not been well installed. It is therefore essential installation is carried out by experienced contractors, is well supervised and follows the relevant guidance.


Some buildings covered by L2 but employ "domestic style" details such as schools or small office buildings may need to employ the "robust construction details" for domestic type constructions given in a guide published in association with the Approved Documents although the guide is mainly applicable to part L1.